Acacia Pendulum

Eilat ( 1994 - 1995 )

Acacia Pendulum - February 1996

Acacia Pendulum - planning

Acacia Pendulum : maquette 1:20
Acacia Pendulum : section across the atrium

Acacia pendulum construction

The transplanting process – Yotvata Desert Rresearch Institute (1994-95)

March 1994 : excavation around the tree, plastic covering, connection of drip nozzle irrigation
August 1994 : reopening, shaping of the root ball, connection of the conic container
December 1994 : cutting underneath the container while holding tension

Transporting the acacia trees to Eilat – February 15, 1995

Due to their size (6.5 m' width) the trees were transported with a police escort while the road to Eilat was closed.

Insertion of the sculpture into the atrium – February 1995

Lifting Acacia Pendulum into its final position – May 1995

The sculpture which weighs 6 tons is suspended from a complex cable installation which divides the load. Bringing the Pendulum into position involved a specially designed pully and lifting system (tirfore)